Construction surveys, explained.

A construction survey puts the approved plan on the ground, checks it while the foundation goes in, and proves at the end that the building went where the permit said it would.

Three stages

One survey that follows the project.

A construction survey is not one visit. It runs from layout before work starts, through checks while the foundation goes in, to an as-built survey when the work is finished.

Using the same surveyor for all three avoids a costly surprise: a second firm finding, at the end, that the first firm's stakes were off.

Layout

The plan, staked on the lot.

In a flood zone the benchmark matters as much as the corners. A floor set a few inches low can fail the flood inspection or raise the owner's flood insurance for the life of the building.

  • Building cornersWith offset stakes, so the layout survives excavation.
  • PilesEach pile located, when the foundation sits on piles.
  • Site plan itemsDriveways, pools, walls and anything else on the approved plan.
  • BenchmarkA fixed point of known elevation, so the builder sets the finished first floor at the height the plan requires.
During construction

Checked before the next step.

Many building departments want proof the foundation is in the right place before the job goes further.

  • Form board surveyWith forms set and before the slab is poured, the surveyor confirms they sit inside the setbacks. Winter Park, for example, requires it at the slab inspection.
  • Spot or tie-in surveyOnce the foundation is in, its location and elevation are measured. Collier County puts a hold on the permit if this is not received within 10 days of the foundation inspection.
  • Under-construction elevation certificateIn a FEMA flood zone, an elevation certificate marked "Building Under Construction" once the lowest floor is set. Hillsborough County accepts a sealed foundation tie-in survey in its place.
As-built

Proof it was built to plan.

When the work is done, the surveyor locates everything that was built: the house, driveway, pool, walls and, in many places, the finished grades. The building department compares it with the approved plan before it issues the certificate of occupancy.

In a flood zone the as-built goes with a new elevation certificate marked "Finished Construction", because the FEMA form requires a new certificate once the building is complete. Charlotte County has required an as-built survey with elevations before a certificate of occupancy since 2008, and St. Petersburg lists the final elevation certificate among its requirements in flood zones.

What to send

What makes the quote precise.

Layout is quoted by scope: a pile foundation or a long driveway takes more field time than four house corners. Whoever holds the permit hands the surveys to the inspector, so the permit holder should own the schedule.

  • Approved plansSite plan and building plans, as PDF or CAD.
  • Permit numberSo we follow the right jurisdiction's checklist.
  • Current boundary surveyLayout ties to the property lines. If you do not have one, we do it first on the same order.
  • Foundation type and scheduleSlab or piles, flood zone or not, and the pour dates.
Questions

Common questions.

Do I need a boundary survey before a construction survey?

In most cases, yes. Layout ties to the property lines, so the surveyor needs a current boundary survey to work from. If you do not have one, it can be done first on the same order.

Is a construction survey the same as an elevation certificate?

No. The construction survey places and checks the building. The elevation certificate is a separate FEMA form, required in flood zones at the plan stage, under construction and at completion. We can do both on the same visits.

What happens if the form board survey shows a problem?

The forms are moved before the concrete goes in. That is the point of checking at that stage: moving forms costs hours, moving a poured slab can cost the project.

Who usually orders a construction survey?

The builder or general contractor, sometimes the owner. The permit holder is the one who must hand the surveys to the inspector.

Quotes

Ready to order?

Send the approved site plan, the permit number and your build schedule. We reply with the scope, price and the dates we can hold.