ALTA/NSPS land title surveys, explained.
What an ALTA/NSPS survey is, what changed in the 2026 standards, how Table A sets the scope, and what to send so the survey is ready before closing.
The national standard survey for commercial deals.
An ALTA/NSPS land title survey follows minimum standards set jointly by the American Land Title Association and the National Society of Professional Surveyors. Title insurers, lenders and buyers use it to see what a title commitment means on the ground: boundaries, easements, improvements and encroachments.
It is the usual requirement for commercial purchases, refinances and development loans. Residential closings rarely need one.
New standards apply to surveys ordered from February 23, 2026.
The 2026 Minimum Standard Detail Requirements took effect on February 23, 2026 and replace the 2021 version for new surveys. Survey orders should now ask specifically for a "2026 ALTA/NSPS Land Title Survey" and list the Table A items required.
- Encroachment summaryA new Table A item adds a table summarizing encroachments, which makes review faster for lenders and counsel.
- Records researchThe standards revise what the surveyor must obtain in recorded documents; title insurers no longer have to provide adjoiners' deeds.
- Negotiated itemsA new open Table A item lets the client and surveyor agree on extra work, such as engineering design data.
The optional items that set scope and price.
Table A is a list of optional items the client selects, usually from the lender's or title company's requirements. Common ones include the flood zone, zoning setbacks, building dimensions, parking counts, utilities and evidence of recent construction.
Each item adds fieldwork or research, so the Table A list is the main driver of price and timeline. Send it with the request and we quote against it.
The faster we have these, the faster the survey.
- Title commitment and recorded documentsThe survey shows the easements and exceptions listed in Schedule B.
- The Table A listFrom the lender or title company, or tell us if you need help choosing.
- Certification partiesExact names of the buyer, lender, title company and anyone else relying on the survey.
- Zoning report, if orderedNeeded for zoning setback and height items.
- Site access contactFor gated sites, tenants or buildings.
What drives both.
Site size, the number of improvements, the Table A items and the condition of the records drive both. A vacant parcel with a short Table A list is far quicker than a multi-building site with utilities and parking counts. Share your closing date and we confirm a timeline that meets it.
Most delays come from the order, not the fieldwork.
A complete order gets a survey that clears title objections on the first draft. Three points catch most teams under the 2026 standards.
- Name the standardAsk for a "2026 ALTA/NSPS Land Title Survey". An engagement letter that still cites 2021 can hold up the deal.
- Update your Table A listThe 2026 standards added an item and renumbered others, so a list copied from a 2021 order may not ask for what you think.
- Send every Schedule B documentA copy of each recorded document listed in Schedule B, Part II. The surveyor can only plot easements they can read.
What to check before you sign off.
Send comments in one round, consolidated across lender counsel and the title company. It is the fastest way to a final sealed survey.
- Schedule B notesEvery item marked as plotted, affecting but not plottable, or not affecting the property.
- Legal descriptionSurveyed description compared with the commitment, with any gap, gore or overlap with adjoiners shown and explained.
- AccessFrontage on a public road, or the access easement the parcel relies on, shown on the drawing.
- Encroachments and setbacksAnything crossing the lines in either direction, and buildings or parking inside setbacks.
- Flood zoneThe flood zone note checked against the current FEMA map panel.
Common questions.
Do I need an ALTA/NSPS survey for a house?
Rarely. Residential closings usually use a boundary or closing survey. ALTA/NSPS surveys are for commercial property and some high-value or complex residential deals.
What is the difference between an ALTA/NSPS survey and a boundary survey?
Both establish the boundary. An ALTA/NSPS survey also ties the title commitment to the ground, follows national standards and adds the Table A items the lender or title company requires.
Which standards apply to my survey?
Surveys ordered on or after February 23, 2026 follow the 2026 standards. Ask for a "2026 ALTA/NSPS Land Title Survey" in the order.
Who chooses the Table A items?
Usually the lender and title company, with input from the buyer's counsel. We can suggest a list if you do not have one.
Can you update an ALTA survey done under the 2021 standards?
Yes. An update contracted on or after February 23, 2026 is done to the 2026 standards. Send us the prior survey: it shortens the records research and the fieldwork.